Having trouble viewing this email? View as a webpage.

West End Neighborhood E-Newsletter [Vanderbilt University]

April 2019

Final exams and move-out

The university held a town hall on April 2 for West End neighborhood residents to discuss ongoing construction activity in the neighborhood and plans for the upcoming end-of-year events such as finals, Commencement and move-out.

Click here for the information and corresponding maps shared at the town hall.

The university as well as our contractor, Layton, understand that living in or near an extensive construction zone is not easy. We continuously strive to balance the needs of the project’s schedule and budget with our student experience and appreciate the patience, understanding and cooperation by the residents in the neighborhood during this time.

During finals week, starting April 23, the university has decided to cease all rock excavation, which produces a loud noise. However, in response to the town hall discussion, the university has decided to suspend construction activities to include:

  • All loud rock excavation at all areas of construction (as mentioned above)
  • All ground level excavation that causes dust or excessive back-up beeping
  • Specific trenching for electrical to Greek Houses on Kensington and Radius Alley
  • Limiting equipment movement that will cause back up beeping. This will be limited to specific deliveries and will be sporadic throughout times from late morning to early afternoon each day but will not be ongoing
  • Hammer drilling into concrete at both West End Neighborhood and RC-A will be suspended
  • Cutting and chopping steel scrap inside RC-A

As noted in the town hall and in the link above, please use the hotline email, Constr_alerts@Vanderbilt.edu and phone number, (615)-343-9675, if you believe noise or activity is outside of the temporary limits put into place.

Move-out 2019 map
Click for larger image.

Commencement

In the event of inclement weather, follow up-to-date details from the Vanderbilt Commencement app.

Commencement 2019 Rain Route
Inclement weather route. Click for larger image.

Construction & Mobility Updates

  • Beautification efforts in the West End Neighborhood continue. This includes work along West Side Row, alleyways and Kensington. Construction on house sites 1, 2 and 3 also continue.
  • Concrete pours will continue through April. Students residing in the Towers and Greek houses will continue to receive emails from Housing in advance of the pours.
  • Fences have been placed around the construction sites noted above.
  • To accommodate construction underway, Parking Services continues to make five floors of the 25th Avenue Garage available to F permit holders. A VandyVans stop was installed at this location and will continue to support increased student traffic in the area.
  • VandyVans stops in the West End neighborhood are located at Branscomb and lot in front of Carmichael Towers East. Slight adjustments may be made to routes taken during construction, but schedules will not be impacted. Be sure to download the DoubleMap app and select Vanderbilt. This allows riders to track the progress of shuttles in real time.
  • Additional short-term and long-term mobility solutions for the area, and rest of campus, will be addressed through MoveVU. Updates on MoveVU will be provided later this year.
  • For parking questions, please contact VUPS Parking Services at (615) 322-2554.

Upcoming Milestones

Milestones are subject to change and updated monthly.

Past milestones can be found in previous issues of the West End neighborhood newsletter. 

April 2019

  • Spring semester classes end on April 22. Examination and reading days begin on April 23.

May 2019

  • Senior Class Day is May 9. Commencement is May 10.

Summer 2019

  • Preparation for demolition of Towers 3 and 4 to begin after Commencement. Demolition to begin summer of 2019 and continue through fall of 2019.

August 2019

  • New NPHC and Zeta Tau Alpha houses to be complete.
  • Primary utility work through West End neighborhood to be complete.
  • Delta Kappa Epsilon house cleared.

September 2019

  • Kensington beautification efforts to be complete in late September.

October 2019

  • New commons/lawn beautification efforts to be complete in later October.

December 2019

  • Community event space, Lambda Chi Alpha, Delta Kappa Epsilon and Kappa Sigma houses to be complete late December, and open for students in January.

2020- 2023

  • July 2020: Complete Residential College A (RC-A).
  • July 2022: Complete Residential College B (RC-B).
  • July 2023: Complete Residential College C (RC-C).

Online Resources

Live Cam

Websites

Videos

Photos

VandySafe App

West End Neighborhood Photos, April 2019

West End Neighborhood, April 2019

West End Neighborhood, April 2019

WEN April 2019

 

Vanderbilt University  |  FutureVU West End Neighborhood  |  421 Kirkland Hall

Subscribe to this newsletter   |  Opt-out of this newsletter

        

Vanderbilt University is committed to principles of equal opportunity and affirmative action.
Vanderbilt®, Vanderbilt University®, V Oak Leaf Design®, Star V Design® and Anchor Down® are trademarks of The Vanderbilt University. ©2024 Vanderbilt University. All rights reserved.